Thursday, August 10, 2017

Jogi's Leaving

After 23 years of service to Granite Bay Golf Club and it's members, Jogi Choung, our long time Assistant Superintendent has accepted the Golf Course Superintendent position at Empire Ranch Golf Club in Folsom.


Jogi came to the United States in 1984 from Punjab, India and started working at Cameron Park CC while attending night school to fine tune his English and Agronomic's. In 1994 Jogi followed Jim Ferrin, Granite Bay's first Superintendent, to help with the growing in of a new Golf Club in Granite Bay. He has been here ever since.

Jogi has always described himself as a "Farmer" and has been the steadying presence in Granite Bay's Golf Course Maintenance Department for over two decades. He is more then just a leader to everyone on the crew, he is a friend. He never raises his voice, always has a smile on his face and has always maintained demeanor that everyone gravitates too. We will all miss him but are happy for him with his new opportunity and that he will still be a part of the Club Corp family.

Jogi's last day at Granite Bay is Tuesday August 15th and we are having a little send away fiesta today, Thursday August 10th at 12:30 PM in the golf course maintenance yard. Anyone reading this that wants to bid Jogi farewell is more then welcome. Miguel & Enrique are making tacos as well.  


Jogi and Matt down in a hole

Jogi making irrigation adjustments via IPad

Saturday, July 8, 2017

75 Days Left of Summer

The Summer of 2017 started off with an intense heatwave here at Granite Bay. The six days between June 28th and July 2nd we averaged 106 degrees for a high. This is the type of heat that will leave a mark on the cool season turf that comprises most of the playing surfaces here at Granite Bay. We did experience a reprieve as the heatwave was thankfully followed by some much kinder weather ushered in by the beloved delta breezes, but the intense heat did leave behind some isolated damage and we have another similar heatwave predicted for this week. Below are a series of pictures that chronicle some of the issues the golf course is currently dealing with along with what the golf course maintenance department is doing to mitigate the damage.

From afar the golf course looks good, has many areas of dense turf and really good color.

However up close in some areas you can see typical heat related issues. Above picture depicts a disease called Southern Blight that we treat proactively for. Obviously our proactive treatments were not enough for this specific patch of Fairway turf on #16.

The heat also plays havoc with cart paths in some areas. Cart path buckling here is caused by soil expansion underneath. The above picture depicts the area directly after the forward tees on #5. There is another raised area on #9. The soil on #5, #8, #9 is somewhat different then the rest of the course in that it has a higher clay content then decomposed granite. The three paths on these three holes are the only paths we have experienced this type of heat related lifting. We will repair by using a concrete saw and remove a 3" section of concrete creating an expansion joint. 

Putting surfaces took a hit from the intense heat as well and are now starting to exhibit the stress from root loss particularly the poa annua patches. The past few summers we have not experienced the type of heatwave we experienced the beginning of July and the poa on our greens fared pretty well. But as I said, 106 average highs temps for 6 days will leave a mark. Above Miguel is hand spiking and seeding weak areas with bentgrass seed on the practice green. In fact we closed the practice green on Friday 7/7/17 as much of the high side of it is thinning. Tilleys practice green is still open.

#7 green has thinned out at the back of the green as well. All of the greens have been spiked to improve air exchange in the root zone and this one has received additional spiking  and seeding as well as placing GUR ropes around the weakest area at the back.

Additionally we have put out the portable fan to help with surface air movement on this troublesome green and have tree trimmers scheduled to thin the Live Oaks behind the green creating more air movement. The past few summers #7 has been pretty good and we thought we might have turned the corner with it. However the heatwave we experienced has highlighted our vulnerabilities and proved there is more work to do. 
The #3 green is at least for now proving to be a success story. Tree thinning allowing for substantially more air movement in the area has really paid dividends on this chronically bad green in the summer months. However if you look really close even in this picture you can see a yellowing of the poa annua patches which is all related to root loss and heat stress.
#3 fan up and running during the summer months contributing to the greens success story.

Many tee boxes on the course were the first visual casualties of the heatwave. The perfect storm of intense heat and traffic took it toll on several tee levels. Picture above depicts the granite level on #1 at the conclusion of the heatwave. 

GCM re-surfacing. We also took the opportunity to expand this level and have plans to expand the level below in the hopefully near future. 

#1 granite level growing in. Hopefully it will be ready for some use in a few weeks.

The granite and club levels on #5 took a hit from the heatwave as well. The hole will play short for you granite and club players while we re-surface.

These tee boxes needed to be leveled and expanded as well. We will finish the expanding and leveling process next week and install the sod.

Your GCM staff will continue the good fight and battle to mitigate further setbacks as we not only deal with issues from the early July heatwave but future heat that the next 75 days of  summer (as of 7/8/17) is bound to bring. Summers are hard on turfgrass in the west and particularly hard on cool season golf course turf.  We cant control the weather but we can manage the irrigation, prevent disease and insect damage as much as we can, re sod areas when able and live with some damage when we have to. 

It's Only 75 Days !

Wednesday, June 28, 2017

Wedgewood Vegetation Management

The community of Wedgewood, our southern neighbors have recently contracted with the Vegetation Management Company, Goat Central to start clearing out accumulated brush for fire prevention in 15 acres of Linda Creek Ravine. Granite Bay Golf Clubs Property line to the left of #14 is adjacent to the area that Wedgwood has hired the contractor. We have allowed the contractor to install temporary fencing slightly onto the golf course property just below the bridge on #14. It will take three weeks to clear  the 15 acres at Wedgewood and I understand afterwards the process will be moving over to Granite Bay Hills. Evidently this is quite common for local associations and large home-sites that have these fuel load reduction needs to utilize Goat Central for this type of vegetation management.




Installing the temporary fence along the actual property line would have been an onerous task and possibly not as a successful containment as installing in the location below our #14 bridge. This Green Vegetation Management Procedure is approved by the  California Regional Water Quality Control Board as well as the US Department of Fish and Game according to Goat Central proprietor Roy Austin. 

Containment fence beginning pin high to #14 Tee.

Fencing traveling through the Linda Creek Ravine below GBGC's #14 bridge.

Crossing over main fork of Linda Creek heading up left side of #14

We have temporarily moved the out of bounds stakes in 5 yards or so to accommodate the fence up the left side of #14. This should take only 3 weeks  and we will get a little berry and poison oak clearing out of it as well.

Tuesday, June 27, 2017

Cart Path #1 Bridge Complete

As planned, we completed the demolition, forming and pouring of the broken concrete near the beginning of our #1 bridge today, Tuesday June 27th 2017. Traffic was routed around #10 to #1 where all play for the day started on the pebble tees. We will have to play that way tomorrow, Wednesday 6/28/17 and will open the bridge to cart and foot traffic on Thursday 6/29/17. Below are some pictures of the process for those who are interested.



Detour over #10 bridge, around #10 to the #1 Pebble Tee

Miguel completing early AM demolition of the existing concrete.

Lifting a big chunk to drop and break


Enrique getting some grading done ahead of concrete contractors. I neglected to get a picture of us digging out the surface Oak Tree roots that caused the damage in the first place. The root material amounted to a couple of cart loads.
GB moving concrete with Toro Workmen.

Dumping concrete into formed cavity

J&S Asphalt concrete crew getting concrete in place.

Concrete finishing
Finished product.
Before



Friday, June 23, 2017

Cart Path Repair #1 Bridge

All of us who play and work at Granite Bay Golf Club have been dealing with a bumpy patch of concrete leading onto the #1 bridge for awhile now and we are finally getting it repaired this coming Tuesday 6/27/17.






The damage occurred gradually from the roots of a maturing Valley Oak that was likely planted 20 years ago right near the entrance to the bridge. 




A small challenge in making this repair is we will need to close the bridge for a day or two while we pour new concrete and allow the concrete to cure. During this time we will need to route all cart and foot traffic to the #10 bridge and around to the #1 fairway. We will have the temporary traffic pattern marked plainly and hopefully not experience major traffic jams on the #10 bridge. 


The detour will add 800 to 900 feet to a walkers round that day so prepare for some extra exercise.


Wednesday, June 14, 2017

Summer Is Here





The Summer Solstice in the Northern Hemisphere is next week on Wednesday June 21, 2017. This marks the beginning of the most difficult time for the cool season grasses which is the type of grass playing surfaces we have here at Granite Bay. Things can get interesting during this time which stretches from the Summer Solstice to the Fall Equinox on Friday September 22, 2017. Why this is the most difficult time for our course is in part due to:

  • Extensive heat causes cool season turf to be more susceptible to disease & insect damage, weed infestation & heat stress and wilt.
  • It is a challenge  to keep the course as firm as we would all like it because of the amount of irrigation required to keep it viable and alive.
  • It is a time of year of high golfing activity which compound the above mentioned stresses.



What Are Our Plans?

We are in pretty good shape going into this stressful summer season and that can go a long  way towards our inevitable success. Currently however there is a heatwave forecasted during 2017 Mac Cup that has six consecutive 100 degree days predicted. Those kind of stretches have always left a mark on this golf course.  So sucess will be sustaining as much turf  as we can through the  summer so as to minimize our recovery efforts in the fall. The plans to achieve this success is twofold: Manage Irrigation & Control Cart Traffic

Manage the Irrigation

Irrigation management is constant. We make daily adjustments to the individual sprinkler head control that has been recently expanded. We treat areas of the course with surfactants or wetting agents that aid in both water movement where where we need to move irrigation into the soil,  as well as retention where the soil needs some help in holding onto the irrigation that has been applied. We shift GCM personnel resources into hand watering because no matter how sophisticated a irrigation system is, there is no substitute for a guy on a hose.  


There is no substitute for a man on a hose


We understand the traditional inconsistencies with areas of the course that can get soft and we are ever striving to improve them as well as micro-managing of the irrigation system in these areas. Our decomposed granite soil's and cool season grass varieties make this a ongoing challenge but I believe we have made progress over the years. That being said it is inevitable that the the ups and downs of a summer season will lead to periods of the course getting on both the wet & dry side. 



Control Cart Traffic

Granite Bay Golf Clubs Scatter Definition is:

Golf Carts can scatter on the course by entering by entering at designated entry points defined by green and white stakes. Once in the fairway you are free to scatter while in and among the fairway. Please exit the fairway or rough at the designated exit point designated by red and white stakes.


Enter



Exit

Additional precautions and strategy's to protect the course besides the scatter rules include restricting traffic to entire golf holes although limiting this practice when we can to only one hole per nine. Additionally when temperatures are forecasted to be over the century mark, we will call for cart path only in the afternoons.


Results of golf cart traffic driving on stressed turf during the summer.

How can Members Help?

By understanding that cart operation on the turf surfaces during the summer months is stressful. Please utilize cart paths as much a possible.  Additionally follow the scatter rule and drive on green healthy grass avoiding brown, stressed grass.


The Drought is Over 

One thing we wont be talking about is drought restrictions in 2017. Due to almost record rainfall  & snow accumulation in most parts of the State, our reservoirs and aquifers have been replenished. However the drought of 2013 has changed the way many of us look at water policy and use. The State will continue to exert it's authority over water purchase and use and we at Granite Bay will have to stay on top of these inevitable changes. We are currently forecasting to be 25% below a State calculated MAWA Water Budget (maximum allowable water allocation) for the 2017 season and have had a good conservation story since this game changing drought of 2013 started.

Current Folsom Reservoir level. 2017 was one wild graph line !

Tuesday, April 11, 2017

Spring 2017 Aeration Progress

Monday 4/10/17 will be three weeks since we aerated the putting surfaces here at Granite Bay. Its been two weeks since we followed up that aeration with a aggressive vertical mowing, seeding and light sand topdressing. On Monday 4/10/17 we applied another light sand topdressing and will continue to do so most Mondays for the remainder of the growing season which has been our practice for the past two years.


#11 green a day after 3/20/17 core aeration


Practice Green on 4/10/17.  21 days after initial core aeration.
By my estimation a little behind.

 After 21 days of aeration recovery I would say the greens are a bit behind the previous two or three seasons primarily due to weather. Since aerating greens we have had 9 rain days producing 4.7" of precipitation. While the rain is helpful after aeration to move sand into aeration holes and into the turf canopy, the accompanying lack of sunlight during inclement weather will hamper growth to cover over aeration holes and germinate seed.


























We were able to stay on schedule with fairway aeration despite all of the weather. Weather did get in the way of getting all of our topdressing out as its need to be dry to drag into the holes. We anticipate drier weather ahead  so we will be able to get the rest of this topdressing out over the next couple of weeks.


Aerating FW


Dragging Cores

Cleaning up the mess

We are taking this week, Monday 4/10/17 - Friday 4/14/17 to core aerate rough areas prior to a nice application of fertilizer to the entire course next week. This will conclude major aeration events until October.


Fairway Topdressing sand stockpiled in the parking lot.