Thursday, February 9, 2012

Driving Range Tee Line Complete

Completed Tee Line ready for play
The execution and completion of the new Driving Range Tee Line went off exactly according to plan. The motivation behind the project was an obvious need to replace the worn out artificial mats that are used for practicing when the driving range is not set up  the 23,000 square feet of grass teeing area.



Concrete forms for raising the
concrete pad.









This half acre of turf has never been able to sustain all of the driving range traffic and we have always needed to utilize artificial turf mats for a third of the member use at the club.  Additionally artificial surfaces are necessary during wet weather and sustained periods of recovery of the grass tee. 

Another issue that had been slowly developing was the concrete pad in which the mats are stationed had become lower then the ever increasing grade of the driving range tee, creating a basin that collected irrigation and rainfall. This situation required a remedy and after considering several options, we decided to raise the concrete pad and install new drainage to keep the new artificial turf from sitting in water.


Contractor pouring the concrete.
Members of the Granite Bay Golf Committee did the initial legwork and steered us in the right direction for the material to replace the old mats. The plan was always to move towards a continuous Tee Line rather then just mat replacement. With that in mind, the "driving range artificial turf sub committee" traveled around the State trying out the best Tee Lines they could find which lead us to Synthetic Turf International (STI), the most recognized brand in the artificial turf industry. STI's Tee Lines are the current standard in the industry and the EZ Turf Hybrid is latest generation, most advanced artificial turf driving range hitting surface available. By design the EZ Turf Hybrid is a little soft when first installed but will firm up slightly, but not too much, so as to maintain the most realistic feel throughout the life of the Tee line. Additionally the choice of a continuous Tee Line versus replacement mats will allow for hitting rotation and a life expectancy of  well over five years for the new turf.



GCM installing new drainage, backing up newly
raised concrete pad.

If you happened to take the time to look at some of the Tee Lines from  STI you will notice some installations appeared to have the regular turf in contact with the artificial turf and in some instances that is actually the case. Others have borders of wooden or recycled plastic 2" X 4" material to provide a barrier for maintenance edging. We felt strongly about some type of border and opted for a recessed area in the new concrete pad for the new Tee Line to sit in and be surrounded with a concrete mow strip of sorts. Built into the pad was a unnoticeable front to back 1% slope to facilitate drainage along with extra expansion joint like drainage channels at the rear of the pad to provide an escape path for irrigation or rainfall. 


Synthetic Turf International of Northern California
gluing down the new artificial turf
Tee Line. 

Real turf is always a better surface to practice on, and this new Tee Line will not change our intent or schedule of having our members practice on the turf Thursday through Sunday. However we all have to admit that the new Tee Line is a substantial upgrade from even replacement of the old, worn out mats and will hopefully not make it as hard to use when GCM inevitably has to close the grass tee for extended renovation and recovery.



                                                                                   

Friday, February 3, 2012

Weather, Winter Progress & Green Speed

I find myself in the position once again to apologize to the members who enjoy the details I cover in these course updates as I have been negligent in updating  for too long. Much has been happening on the golf course as many have witnessed so I will briefly try to catch up with pictures along with sharing some details.

Strange Weather
Weather is the one variable that we all deal with and is the one factor from season to season that effect the golf course playing surfaces the most. Normal high and low temperatures, precipitation, humidity are accumulation averages over a several years that don't seem to mean that much as the here and now of our playing surfaces and how they are performing based on the weathers influence. Case in point, last winter the course experienced above average precipitation and played much  slower then the fast and firm surfaces we are experiencing this winter season. I have always believed that  the uncertainty of the weather, something we have absolutely no control over yet has the dramatic effect on the surfaces we play this great game from, is a big part of the games charm.  So we take what we get as far as the weather is concerned. What other choice is there? 

Generally speaking  these cool, dry weather patterns will always provide the best playing surfaces for Granite Bay. The logic is simple. If its cool, the turf grass is not growing and has minimal  to no irrigation requirements. If it is dry, playing surfaces firm up. The combination of minimal growth and minimal moisture produces less leaf surface and friction combined with the above mentioned firmness and we get the surfaces that most players love. GCM (golf course maintenance) loves these conditions as well because there is allot less effort involved in providing the surfaces that most players desire shifting our efforts to other tasks that beautifies the course along with making it easier to take care off during the upcoming summer, something we always have our sights on.

Although much of the winter has been cool and dry, a
recent storm in late January brought almost 4" of rain
over a few days. This is the front of #13 during a storm.

Green Speed
Of course the most noticeable surface is the putting surface. We have been experiencing green speeds in the 12 foot range almost all winter. The above mentioned weather scenarios can claim most of the credit as cooler weather slows growth rate down and lack of rain firms things up along with allowing GCM  to roll the surfaces more frequently. However I believe  much of the recent firmness of our putting surfaces has more to do with aggressive aeration that we have employed over the last year and a half then the  increased rolling and decreased rainfall. Ten percent of our greens surface are has been removed on each aeration event totaling 30% since we started aggressive aeration. All of this removed organic matter was displaced with  topdressing sand and many of you have told us that you have noticed a progressive firming of the greens as evidenced by lack of foot printing which has been our observation as well. We have also observed less disease activity, a virtual elimination of anaerobic black layer and just a healthier condition in which the turf responds to fertility and other inputs accordingly.


Jogi checking green speed on #9 with stimp meter.

What does show up very well at this time of the year on our greens is the poa annua population. The reason for this is that in colder weather, particularly frosty and frozen weather, the bentgrass on our greens slows down to almost a complete dormancy where as the poa is still growing and beginning to thrive. If it seems like the poa population is greater on our greens then it has been in the past, it is probably because it is for the most part. Unfortunately it is the nature of the beast to continue its encroachment no matter what strategies we employ to push it back. Bottom line, it is not uncommon for poa annua and bentgrass to coexist on putting surfaces that are the age of ours which is coming up on 18 years. Pure bentgrass greens are something special to putt on, particularly the new bentgrass varieties however there are some very good putting surfaces in  the world of golf that have a substantial amount of poa annua in them. What is difficult to maintain with a poa-bent or bent poa surface, depending how you look at it, is consistency.



#10 Green exhibiting a 50/50 bentgrass-poa mix.
The poa is the brighter green patches.
The bentgrass is the more grey-green.

Granite Bay's putting surface consistency from season to season & day to day admittedly has been elusive. However the progress made in organic matter reduction in the top 3" of our surfaces via core aeration in the spring and fall sets up better success when it comes to consistency because the overall health of the surface is better. Our goal for these surfaces in 2012 is to maintain consistent, smooth ball roll with speeds between 11 and 12 feet by:


 
  • Continue aggressive core aeration Spring and Fall.
  • Better control over poa annua seed head utilizing growth regulator applications.
  • Consistent surface management strategies including brushing, vertical mowing & light topdressing.
  • Continue successful walk mowing and rolling regimen
  • Fertility strategy that includes acidification which will refine leaf blades (make them skinny and wiry) reducing friction and increasing ball roll without the need to lower the height of cut.
The coexistence of bentgrass and poa annua in relation to the quality of the putting surface is a topic unto itself. Short of re-surfacing, we have to work with what we have in the  here and now. The above strategies can and will produce scenarios where the bent will thrive at certain times in the season and the poa thrive in others. Bottom line if the surfaces are healthy, firm and ball roll is consistent and true, we will have achieved our goals and membership will have surfaces that are fun, challenging and can be proud of.

A Picture is Worth a Thousand Words
Because I have admittedly been negligent in updating details of GCM activities of late, I thought I would catch up with pictures and  brief associated details.


Recently cleared rocks below the upper tees on #14.
Unfortunately I don't have a real good before picture
however I think we all remember the berries and
scrub oak that completely covered these beautiful rocks.

Working on the left side of the lower bridge on #14 primarily
to facilitate out tree service contractor so they could top the
live oak that are close to blocking the hole from the upper tees.


Starting to clean the outgrowth on the right hand side
of #14 below the lower tees.


Finished view from the club tees on #14 after clearing.
The straw area is covering for fescue seed and the straw
waddle at the top of the cleared area is to prevent erosion
during rainfall. The 4" storm in late January didn't erode
the area at all.


Newly constructed nursery area to the left of #4 on the
corner of Barton and Roseville Parkway.  The area was
actually irrigated for a nursery area but had overgrown
so we cleared the overgrowth, completely re-did the irrigation,
graded the rough area along the Parkway and organized
the entire area for processing the the large amount of
green waste that is developed on a course like Granite Bay.
In the nursery area we will establish sod for our greens with
cores removed from this springs aeration, grow our own  native fescue
and use the area as a storage area for purchased sod.


The large pieces of the old concrete removed from #18
when we installed the path to the upper tee. These concrete
pieces were hauled over to the area that we made into the
nursery / recycling area and have now been used to
retain a bank.


Repairing the front lip on the large bunker in front of #1 green.
When we renovated the bunkers not that long ago we did some sod work
around the bunkers edges, but our primary focus was to replace drainage,
install liner and replace the sand. Now that the bunkers have sand
in them, as opposed to virtually none prior to renovation, we are
experiencing a accelerated buildup of sand on the front edges that
need to be fixed on some of our bunkers. When we do this work we
also "softening" the front lip of the trap with the goal of mitigating
some of those unplayable lies in the hazard.


#1 complete with new sod. Other bunkers we plan to address
in February are the two on #14 and the two on #13.



Looking down on another area that needed some clearing work
to the right and pin high to the green on #14. Its cleaner,
easier to find you ball but still a pretty tough shot.

Irrigation enhancement around the bunkers on #14.
we did replace the little pop-ups during renovation on these
bunkers 3 to 4 years ago but are not happy with their
performance. I know it seems like we were just working there
and we we're I suppose although I will tell you that everywhere
we have installed the type of sprinklers we are installing
here it has made a HUGE difference in turf quality
and our ability to maintain these areas in the summer. The vast
majority of this work was done last winter but we still have
more to do.

Forming the new raised pad for the new continuous Tee Line
of artificial turf. Raising of this pad was necessary as the pad
was low and collected water as the turf around it raised over
the years from topdressing.

Pouring the concrete.

GCM installing drainage behind newly raised
driving range tee pad.


GCM installing sod to back filled raised pad.

Newly renovated tee markers. The motivation behind renovating
our tee markers was first and foremost our tee markers were
old, stained and in dire need of replacement. After pricing new ones
we concluded that this was a "more for less" opportunity and started
playing with different epoxies, colorants, sands and have now come
up with what we think is a better, and substantially more economical
duplicate version of Granite Bay's tee marker. The red and purple
markers you currently see on the course are actually renovated
markers that we have cleaned up, colored and treated with epoxy
and replaced on the course. The next markers you will start to see
on the course will actually be ones we casted ourselves.

Along the same motivation of the tee markers we priced sign
replacement for the many signs around the clubhouse and on
the course and decided to purchase a computerized
carving machine and do them ourselves. All signs around the
clubhouse have been completed and we are currently working
on signs on the course.

The first phase of signs going out on the course. We changed
color themes to blend with the divot boxes and course water
dispenser enclosures. Additionally we have started to add
Audubon signage to the course which is an actual requirement
of belonging  to Audubon. It does not fit, nor is it our intention
to increase the presence of signs at Granite Bay, just replace
the worn our wooden signs along with proudly displaying our
Audubon Signature status.

Communication
I hope your opinion is that as a club we have come  along way as far as providing and distributing information about what going on around the club and on the golf course. This course update, the very popular daily  Golf Shop update which is distributed daily to over 300 members, the brand new Granite Bay Golf Shop blog are just some of the information and promotional pieces associated with Granite Bay. I totally get that not everyone is interested in the "grass growing, vertical mowing, cinch bug" details of golf course maintenance and I for one am sensitive to overloading peoples inbox with web links and attachments ect ect ect. Additionally it becomes a task to update course details  primarily because I wait too long and then the update itself becomes lengthy rather then short and sweet on a weekly or semi weekly basis. So I am going to adopt the strategy of Heather and Brad with their new Golf Shop update. Anyone interested in receiving notifications when this blog is updated simply add your e-mail to the "follow by e-mail" in the upper right hand corner so you can be automatically updated through your inbox.  This way whoever wants to see the information can get it, and I can update it briefly and frequently without worrying about being a pest.

Friday, October 28, 2011

Aeration Progress Fall 2011

One of the best things that can be done to sports turf such as golf course playing surfaces is core aeration because it addresses multiple issues. The process relieves soil compaction resulting from vehicle and foot traffic. It provides necessary air to the  turfgrass root zone for basic plant physiological processes and maintains soil permeability providing a release passage for the carbon dioxide gasses produced by the roots in these processes. Finally core aeration removes the excessive organic layer or thatch that turf produces which is the culprit that seals the root zone off from atmospheric air to begin with. If it seems like a vicious circle, it is. Insert Granite Bays  heavy decomposed granite soil along with high bentgrass population in the fairways and you have a even higher premium on getting this job done on a regular basis.


Recently core aerated green #12
 The  actual process of aeration is not without its complications and is capable of temporarily harming as much as it helps. This is the reason why the job has to be done in a non stressful time of the year such as Spring and Fall facilitating rapid recovery. The quicker we can get the job done, the quicker the turf will  recover and you can get back to playing on smooth surfaces.

With all of this in mind Granite Bay management, with the blessing of the Granite Bay Golf Committee, decided to expand some alternating front nine / back nine closures to help golf course maintenance get the job done to all of the playing surfaces in not only a expedient manner but producing a better quality job because we would not have to rush to remove wet cores ahead of play. Unfortunately some unexpected early season storms necessitated a change of plans although we were still able to make substantial progress and improvements over aeration seasons of the  past.

Our original plan to aerate greens was to do the front nine on Tuesday the 4th and the back nine on Wednesday the 5th. A decent rainstorm was forecasted for Tuesday night through Wednesday so we decided to close the entire course and complete greens aeration on Tuesday ahead of the storm. This ended up being a good call as the rain started to fall as we were putting the finishing touches on #18 Tuesday evening. Ultimately the recovery of the greens went well. After 21 days aeration holes were completely covered, the greens were rolling smooth albeit not as fast as we would like but most importantly  they are healthy going into the winter.

We were scheduled to aerate fairways with another alternating front nine / back nine closure immediately following greens aeration on Thursday & Friday but conditions were not dry enough to proceed. The following week we stayed on schedule despite more rain and aerated and over seeded  the hybrid bermuda tees. The week of October 17th we were scheduled for our last front nine / back nine alternating closure to aerate around the green surrounds but instead had to use these scheduled dates to complete fairways due to being rained out two weeks prior.

Just a minimal of cleanup following the core processor.
For fairway aeration we borrowed a piece of equipment called a core processor. This machine picked up and ground into a fine topdressing the extracted cores from the aeration process. We divided manpower resources creating a early morning aerating crew and a afternoon / evening cleanup crew  and core aerated all fairways in two days along with doing a much cleaner job. Fairway aeration alone would have normally taken two weeks to complete so in three weeks we completed greens, tees and fairways.  Currently we are aerating a couple of green surrounds a day and cleaning up the mess in the midst of players. It will take us a couple of weeks with everything else we have to do to complete the surrounds. Finally we will start aerating the rough after that which will take another couple of weeks.


Toro Core Processor
converting plugs into usable topdressing


Raccoon damage almost seems to coincide
with fairway aeration.













Obviously the critical task of aeration requires  much planing and preparation. However it is difficult to plan   for everything such as weather or unforeseen equipment malfunctions. Additionally the process seems to create an environment conducive to an increase in skunk and raccoon activity particularly in the fall even with preventive treatments for the insects they long for. But even with these set-backs and unforeseen problems, we have made progress in this aeration season and it is my belief that with the proper equipment and a little luck from  nature, we can aerate this entire property in 5 weeks. We'll give it a try again in the spring.



Pretty substantial hydraulic leak from aeration equipment
on the #3 green. Does not look too bad from this picture but
this area would have died.

Current view after re-sodding the oil effected area.
Temporarily mowing at a higher height of cut then
the rest of the green allowing the new sod to root.
Practice Area Progress
Establishment of the new turf in the recently renovated practice area is coming along well for most of the area.  The hybrid bermuda that we established as a base from sprigs has exceeded our expectations and has rooted and created a very stable  playing surface. It has recently been over-seeded with ryegrass to provide winter color as the hybrid will go at least partially dormant once we start to get some frost and real cold weather. Additionally the ryegrass will help define rough from the tighter mowed areas in front of the target green.

The  expansion of the target green did not establish as rapidly as the rest of the area and still has a ways to go to be close to the quality of the greens on the rest of the the course. We are currently mowing it at a higher height of cut and have re-seeded and topdressed several times since initial seeding in late August.  The cooler weather we are currently experiencing gives us better temperatures to work with and push the green towards usable establishment. Unfortunately there are too many areas on the green that are currently too thin to hold up to ball marks and foot traffic so we have to give it a few more weeks to further establish.

According to our own Craig Johns, "The Golf Committee is working on an event to celebrate the "official" opening of the remodeled Short Game Practice Area some time November that will provide some fun and interesting skills challenge competition….rumor has it that the Golf Channel is negotiating the television rights to "Big Break Granite Bay" to coincide with that….stay tuned for more information about the event."


Very recent picture of the expanded target green in the practice area.
Still not quite ready for extended use.

Next After Aeration
After we complete the aeration of the green surrounds, which will be the week November 7th, we will start pruning and clearing brush. The first area we plan to tackle is area directly in front of the Granite & Tournament tees on #14 along with the vegetation blocking the right side of the hole from the Club & Pebble tees. We plan to make a major push on this kind of work throughout the course this fall and winter  so many more details  and before and after pictures to come.

#14 view from the lower tees.
Our goal is to re-establish the original view from the tee

#14 view from upper tees.
Vegetation in front of the granite tee has been getting out
of control for awhile. We have all seen original pictures with
the bridge below actually visible. Re-establishing that view is our goal.













Tee Rotation
One last thing that you will begin to notice today is that golf course maintenance has started a tee rotation schedule corresponding with our traditional pin rotation. This rotation is in response to a long standing member request and I must apologize that it has taken this long to get something done.  The rotation does move blocks up and down on a regular basis on tees like #5, #6, #7, #14, and #18 mostly for Club and Granite  teeing locations although Tournament and Pebble will have some different shifts in teeing area as well. As an example once in the six stage  pin rotation the Club tees will be moved up to the 439 level on #18 as well as once in the rotation the Granite tees on #14 will be moved down to the 165 level. When these types of shifts occur we have signs that we will place on the tees directing members. I anticipate this being a work in progress for both the GCM staff and membership so bear with us and please provide feedback. The end result of this new rotation schedule should provide more variety for our membership along with rotating wear on our tee boxes by taking advantage of the various tee levels we have here at Granite Bay.


Example of signs we will use to direct members
when tee markes are shifted to diffrent tee levels.


Friday, September 23, 2011

Fall is Here

Today is the day we have circled on our calenders all year long and that is the fall or autumnal equinox. This  day marks the end of summer where the length of night and the length of day are more or less equal. "We have an equinox twice a year – spring and fall – when the tilt of the Earth’s axis and Earth’s orbit around the sun combine in such a way that the axis is inclined neither away from nor toward the sun." (Deborah Byrd, Earth Sky - A clear voice for science 9/22/11) The most stressful time of the year for Granite Bay or any course with cool season turf is from the summer solstice to the fall equinox hence the circle on the calender and sense of relief.


What does this mean for the course? It means that the potential for drastic turf loss due to summer stress is moving behind us. It means that even those little areas of turf that have experienced thinning this year will soon start to recover. Even though this can be the most difficult time of the year to irrigate, the fall equinox means that our soft areas will soon start to firm up.

2011 Summer in Review
This has always been a good time of the year for me to review  summer success's along with setbacks and set goals for the future summers. The course is not in perfect shape as we conclude September, but for the most part not bad especially when compared to summers past. By any ones account the success's we experienced at during the 2011 summer are mostly attributed to the mild temperatures we experienced. The course's weather station only recorded 5 days over 100 degrees and most of these were separated by days if not weeks. There were no 100 degree days in August and only 2 in July. In comparison the courses weather station recorded only 8 days over 100 degrees in 2010, 15 days in 2009 and 13 days in 2008. The total of days over 100 degrees do not tell the whole story of the severity of a summer but can be a gauge we can all relate to, because when it's over a 100, it's hot.
#10 from the clubhouse roof. August 2011
Admittedly the mild summer temperatures was the secret to our success in 2011, however the plans we put in place to combat some of the substandard conditions we experienced last season did make a difference and should help  in future summer months moving forward. These included aggressive core aeration of all of the turfgrass surfaces, substantial irrigation enhancements particularly around the greens, a stepped up emphasis on hand watering and a different approach to disease and insect prevention. The dynamic, growing nature of turfgrass and its surrounding vegetation makes golf course maintenance a perpetual work in progress and it of course difficult to predict the future. We can however predict that next year there will be another summer and it most likely will get hot. So for now we embrace summers like 2011 and at the same time  continue to remain diligent in making  improvements  in preparation for the next one.
Green surround on #9 in August looking pretty good.
Now we just have to do something about that algae
in the pond.
Other accomplishments have been made in 2011 that set us up for future successes as well.  The completion of our sand trap renovation along with completing the resurfacing of our tees  will really free up resources and provide added focus on  more consistent putting surfaces and firmer end of season conditions. We will be discussing the details of how we plan to achieve these goals moving forward  but wanted to reiterate to our members that these goals have been and still remain a priority. We are  looking forward to spending  more time in these areas and  making a difference.

However 2011 is not over yet and we have plans for the remainder of the year. These plans include first and foremost more brush clearing. The  clearing and pruning will start shortly after course aeration in front of the rear tees on #14 and continue in what I call the 13,14,15 triangle. This is that large area of native vegetation bordering right of #13 & #14 and left of #16. Along with this area there is also some pruning work that needs to be done on the left of #13 & #14 as well. 

Fairway aeration process.
2011 Fall Aeration

On July 12th 2011, the Granite Bay Golf Committee unanimously approved additional alternating front nine / back nine closures beyond our normal alternating dates for putting surfaces to accommodate core aeration of the fairways and green surrounds. I mentioned the details of this request in the July 8th Granite Bay Course Update. As I mentioned in the update, my request was based on  the overriding principle that the cleanup of extracted cores during aeration must be allowed to dry for effective processing and the most productive and least obtrusive  way to achieve this is to allow for some additional F9 / B9 alternating closures. 

Hopefully the vast majority of the membership will see the upside to these additional alternating closures such as:                        
  • Quicker Recovery. Rapid  and even recovery of  fairways and surrounds due to as an example, finishing all fairways in two days rather then stretching them out for close to two weeks.
  • Better Job. Much more effective cleanup  due to being able to wait for the plugs to dry before the removal process. 
  • Timely Completion. We potentially can finish core aeration of the entire property in 5 to 6 weeks as opposed to 9 to 12.
  • No Complete Closure. The entire golf course will never need to be completely shut down.


In talking with Brad and Mitch, here is the schedule we plan on utilizing this coming October. Our plan is to try this schedule, evaluate the results, solicit Member feedback and then plan accordingly for future aeration cycles.
  •  Week of October 3-7
Tuesday 10/4/11  Core aerate front nine greens. Traditional GB F9 closure
Wednesday 10/5/11 Core aerate back nine greens. Traditional GB B9 closure
Thursday 10/6/11 Core aerate front nine fairways. New F9 closure
Friday 10/7/11 Core aerate back nine fairways. New B9 closure
  • Week of October 10-14
No alternate F9 / B9 closures for this week. We will however be aerating and overseeding tees and  the hybrid bermuda approaches on #14 & 16, working ahead of, during and around member play.
  • Week of October 17-21
Tuesday 10/18/11 Core aerate front nine putting surface surrounds. New F9 closure
Wednesday 10/119/11 Core aerate back nine putting surface surrounds. New B9 closure 
  • Weeks of October 24-28 & November 1-11 (3 weeks)
No further F9 / B9 closures planned. GCM will be working on core aerating all rough areas  ahead of, during, and around member play.


In conclusion we are adding 4 alternating closure dates to our aeration schedule but are hoping to complete the entire task more efficiently and cleanly in 5-6 weeks rather then 9-12.


Practice Area Progress


The newly renovated practice area is coming along nicely. The hybrid bermuda sprigs surrounding the green came in better then expected. Most areas are enjoying turf coverage of over 50% and the rest is coming on strong due to the aggressive stolons and rhizomes (creeping stems and roots) of the  hybrid bermuda. Its ability to cover bare ground is unsurpassed particularly with the warm weather we have been experiencing and it has been fun to watch the area transform so quickly. Soon we will overseed with perennial ryegrass  for winter color and after some grow in time we will be open for business. The only setback I currently see is the not as rapid establishment of bentgrass seed on the target green expansion.
Practice Area prior to renovation







Practice Area during construction 8/2011.












The expansion of the putting surface is definitely coming slower then the hybrid bermuda around it. Even though established bentgrass tends to be fairly aggressive in our summer climate, germinating bentgrass seed would prefer a little cooler weather. Our initial seeding was just over three weeks ago and we have applied a second seeding just recently which should germinate shortly especially with the upcoming weather changes.

Just prior to sprigging on 8/24/11



Hybrid bermuda filling in nicely 26 days
after sprigging on 9/19/11.
















New Divot Mix

Some of you might have noticed a new divot mix starting to surface in the divot bottles and on the course. We built a large bunker in the maintenance yard to store sand during sand trap renovation.  Now that this renovation is complete, we can use this bunker to mix and store a divot mix for divot's and course repair rather then just straight sand. This 50/50 sand - compost blend will aid in the germination of seed  which is added to the mix along with providing a camouflaged appearance on the course as opposed to all of the white patches.  The current mix might have a little too much compost in it so we will continue to fool around with the recipe of our blend until we find just the right mix for Granite Bay.





















Rolling out this new mix just happened to coincide with a recent "Sand-n-Seed" Outing hosted by the Granite Bay Golf Committee. The following is an excerpt from a re-cap of the outing provided by Craig Johns.


"The first installment of the "Sand-n-Seed" Outing was, from my perspective, a fantastic success.  Although the head-count was only 18½ people (my four year old, Jackson counting for the "half"), it seemed as if there were dozens of folks out, enthusiastically helping to improve the conditions of our golf course.  My personal goal for the evening was to get six holes of divots filled, the crew was able to finish the entire Front Side just as dark descended.  And while we didn’t fill in 100% of the divots on those nine holes, an unscientific assessment (after checking out the course this afternoon) is that we managed to get about 90% of them."



I was concerned / curious about how the group would view the new divot mix because it is a bit pungent but reports were that the group liked the appearance of the mix on the course as opposed the straight sand despite the bouquet. One consequence that I have noticed with the mix as opposed to straight sand is that if a divot is filled to high and not smoothed before it gets irrigated, when the mowers go over the wet mound of mix it leaves a streaking mark that is not the most attractive.  I think getting more sand in the mix will help with this situation along with smoothing out the mix. Our Thanks to everyone who volunteered. I look forward to being a part of the next outing.
 
Large mixing bunker with new divot mix.
Conclusion
Thank you for the kind words and support of our efforts in providing the membership a course you can be proud of. It is our hope and desire to build on the success's of this 2011 summer and create even better conditions for  future summers. This would not be possible without your support. Thanks again.