Back in the Bunkers

As scheduled we resumed bunker renovation this week. We started on the left-hand green side bunker on #11. At a recent golf committee meeting we prioritized the order we will renovate the remaining green side bunkers the remainder of the year. That prioritization is: #11, #10, #13, #15, #4, #8, #17, #12, and #9.

Begining construction left hand green side bunker #11